Question: Peyton is the project manager on a large ERP project. The project will span several years and cost millions of dollars. As part of the

Peyton is the project manager on a large ERP project. The project will span several years and cost millions of dollars. As part of the risk analysis, Peyton has hired a consultant to perform a Monte Carlo simulation. What type of risk analysis is t he consultant doing? Qqantitiaitve Analysis Qualitative Analysis Quantum Analysis Quotient Analysis