Question: Pharoah Construction was awarded a contract to construct an interchange at the junction of two major freeways in a Canadian city at a total contract
Pharoah Construction was awarded a contract to construct an interchange at the junction of two major freeways in a Canadian city
at a total contract price of $ The estimated total cost to complete the project is $ and it is expected to take
two years.
Using the percentageofcompletion method and the costtocost basis, prepare the journal entry to record construction costs of
$ for the frst year.