Question: pic 3 PL 2/2 Seved Consider the precedence network diagram. The numbers above the nodes represent activity durations (in days) End Suppose that after 12

pic 3 PL 2/2 Seved Consider the precedence
pic 3 PL 2/2 Seved Consider the precedence network diagram. The numbers above the nodes represent activity durations (in days) End Suppose that after 12 days, activities 1.9, and 2 have been finished activity 3 is 75 percent finished and activity 10 is half finished. How many days after the original start time would the project finish? The project should finish days from the start