Question: Pilot Implementation Plunge Implementation Parallel Implementation Phased Implementation Match each of the options above to the items below. Uses both the legacy system and new
Pilot Implementation Plunge Implementation Parallel Implementation Phased Implementation
Match each of the options above to the items below.
Uses both the legacy system and new system until all users verify that the new system functions correctly
No answer
Assigns a small group of people to use the new system until it is verified that it works correctly, then the remaining users migrate to the new system
No answer
Discards the legacy system and immediately migrates all users to the new system
No answer
Installs the new system in phases for example, by department until it is verified that it works correctly
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock