Question: Pioneer Rivet Inc. ( PRI ) is a small machine shop that produces sheet metal products. It had one line dedicated to the manufacture of

Pioneer Rivet Inc. (PRI) is a small machine shop that produces sheet metal products.
It had one line dedicated to the manufacture of light-duty vent hood shells, but
because of strong demand it is looking to add a second line. The new line would make
use of higher-capacity automated equipment but will consist of the same basic
processes as the current line. The new line is promised to reduce WIP by 25%. The
current line was able to produce an average of 315 parts per day in the past three
months. The new line is promised to average 500 parts per day.
Current Line New Line
Process
Number
of
machines
per
station
Average
Time
(minutes)
Standard
Deviation
of
process
time
Number
of
machines
per
station
Average
Time
Standard
Deviation
of
process
time
Punching 44110.500.1
Braking 450.7510.500.25
Assembly 230.2510.480.15
Finishing 11.20.1510.480.1
In the current line, the punching and braking stations are stopped for 6 minutes every
hour for maintenance. The new line is very reliable and the machines need not be
stopped during the shift. Maintenance may be performed after the shift hours.
The current line costed the company $5 million, 5 years ago and may be used for
another 2 years, before the maintenance and other costs are so high that the line has
to be retired and replaced with an identical line. The new line is estimated to cost
$7.25 million and would last 10 years. The bank charges 7.5% interest on borrowed
money.
PRI has hired a consulting group to analyze the entire scenario to the extent possible
and provide an outlook for both the current and new line and provide
recommendations on whether it is a good idea to invest in the new line. PRI is also
open to recommendations involving improving their processes.
1 Adapted and modified from Factory Physics by Hopp and Spearman.
Data such as working hours in a day, number of days in a month, etc. may be assumed.
Arrival process and arrival process variability may also be assumed. However, these
assumptions should have a backing; we felt like it is not an acceptable reason for
making an assumption

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!