Question: pipeline ( in - transit ) inventory Average Customer Demand: 1 0 0 units Standard Deviation of Customer Demand: 1 0 units Supplier Lead Time:

pipeline (in-transit) inventory Average Customer Demand: 100 units
Standard Deviation of Customer Demand: 10 units
Supplier Lead Time: 9 days
Desired Service Level (order fill rate): 98.5%
Z score for 98.5%: 2.17