Question: PIPELINES INC HAS WON THE PIPE INSTALLATION CONTRACT IN A SECTION OF 1,000 M TO BE COMPLETED IN 100 DAYS WITH A TOTAL BUDGET OF
PIPELINES INC HAS WON THE PIPE INSTALLATION CONTRACT IN A SECTION OF 1,000 M TO BE COMPLETED IN 100 DAYS WITH A TOTAL BUDGET OF $100,000.00 THE ANALYSIS IS CARRIED OUT TODAY BEING ON THE 30TH DAY OF EXECUTION 400 M INSTALLED AND $20,000.00 HAS BEEN SPENT.What is the earned value? actual cost?CPI? AND SPI