Question: Pipes are installed in a process with two resources. The first resource has a capacity of 0.62 pipes per hour. The capacity of the second
- Pipes are installed in a process with two resources. The first resource has a capacity of 0.62 pipes per hour. The capacity of the second resource is 0.38 pipes per hour. The first resource has 8 workers, and the second resource has 8 workers. One additional worker is hired who is as productive as the current workers.
What is the new capacity of this process?