Question: Pipes are installed in a process with two sequential resources. The processing times for the resources are 2.90 and 6.70 hours. Instruction: Round your answer

Pipes are installed in a process with two sequential resources. The processing times for the resources are 2.90 and 6.70 hours.

Instruction: Round your answer to 2 decimal places.
What is the capacity of this process in terms of pipes per hour? ? pipes per hour