Question: pla calculate slack time from A to G Activity Immediate Predecessor(s) Time (days) A 2 B 6 1 D B 10 E A, D 4
pla calculate slack time from A to G
Activity Immediate Predecessor(s) Time (days) A 2 B 6 1 D B 10 E A, D 4 F 5 G E, F 10 Owuo nt project are B-D-E-G. project = 30 days. Slack Time Activity A