Question: Plan E: Keep the current workforce, which is producing 1,600 units per month, and subcontract to meet the rest of the demand. Subcontract cost is

Plan

E:

Keep the current workforce, which is producing

1,600

units per month, and subcontract to meet the rest of the demand. Subcontract cost is

$75

per unit. Subcontracting capacity is limited to

500

units per month. The warehouse and overtime constraints from Plan D do not apply to this plan.

Part 9

Plan E

Month

Demand

Production

(Units)

Subcontract (Units)

Ending Inventory

0

December

200

1

January

1,500

1,600

5050

enter your response here

2

February

1,500

1,600

7575

enter your response here

3

March

1,800

1,600

3838

enter your response here

4

April

1,900

1,600

3737

enter your response here

5

May

2,100

1,600

enter your response here

enter your response here

6

June

2,100

1,600

enter your response here

enter your response here

7

July

1,700

1,600

enter your response here

enter your response here

8

August

1,400

1,600

enter your response here

enter your response here

Part 10

The total subcontracting cost =

$enter your response here.

(Enter your response as a whole number.)

Part 11

The total inventory holding cost for January through August =

$enter your response here.

(Enter your response as a whole number.)

Part 12

The total cost, excluding normal time labor costs, for Plan E =

$enter your response here.

(Enter your response as a whole number.)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!