Question: Planned lead time for purchased items is _ _ _ _ _ _ _ _ . Choose the correct option to complete the above statement.

Planned lead time for purchased items is ________.
Choose the correct option to complete the above statement.
Group of answer choices
the setup time plus processing time plus waiting time.
the setup time plus materials handling time plus waiting time.
the time difference between when the order was issued and when it would be received from the supplier.
the order processing time.