Question: Planning factors in MRP affect the overall system performance. Which one of the following is not a lot - sizing rule than can be assigned

Planning factors in MRP affect the overall system performance. Which one of the following is not a lot-sizing rule than can be assigned to each quantity before planned receipts and planned order released can be computed?
Economic Production Quantity (EPO)
Periodic Order Quantity (POQ)
Fixed Order Quantity (FOQ)
Lot-for-Lot (L4L)