Question: Please also answer these: B.) The bottleneck time is ??? minutes per unit (round up to two decimal places) C.) What is the throughput time

Please also answer these: B.) The bottleneck timePlease also answer these:

B.) The bottleneck time is ??? minutes per unit (round up to two decimal places)

C.) What is the throughput time of the overall system

D.) If the firm operates 8 hours a day, 20 days per month, what is the monthly capacity of the manufacturing process?

A production process at Kenneth Day Manufacturing is shown in the figure below. The drilling operation occurs separately from, and simultaneously with the sawing and sanding, which a one of the three assembly operations (the operations are in parallel). 5 units/hr 5 units/hr Assembly 0.7 units/hr Sawing Sanding Assembly Welding 2 units/hr Drilling 0.7 units/hr 2.4 units/hr Assembly 0.7 units/hr a) is the bottleneck

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!