Question: please answer 1.3 throughly and clearly - 1.3 This year, Benson, Inc., will produce 57,600 hot water heaters at its plant in Yulee, Florida, in
please answer 1.3 throughly and clearly
- 1.3 This year, Benson, Inc., will produce 57,600 hot water heaters at its plant in Yulee, Florida, in order to meet expected global demand. To accomplish this, each laborer at the Yulee plant will work 160 hours per month. If the labor productivity at the plant is 0.15 hot water heaters per labor-hour, how many laborers are employed at the plant