Question: please, answer 5 (B) only 5. Consider the project with the following dependency matrix. Activity Predecessor Activity Time (day) A1 2 A2 A1 4 A3
please, answer 5 (B) only
5. Consider the project with the following dependency matrix. Activity Predecessor Activity Time (day) A1 2 A2 A1 4 A3 A1 3 A4 A1 2 A5 4 A2, A3 A4, A5 A6 5 A. Compute the earliest completion time of the project using EST and ECT. (15 Points) B. What is the total slack time(s) of the project? (15 Points)