Question: Please answer 6.4 & 6.5 with excel and show work 6.4. An order for 50 of a product is processed on work centers A and

Please answer 6.4 & 6.5 with excel and show workPlease answer 6.4 & 6.5 with excel and show work

6.4. An order for 50 of a product is processed on work centers A and B. The setup time on A is 45 minutes, and run time is 4 minutes per piece. The setup time on B is 30 minutes, and the run time is 5 minutes per piece. Wait time between the two operations is 8 hours. The move time between A and B is 60 minutes. Wait time after operation B is 7 hours, and the move time into stores is 2 hours. Queue at work center A is 40 hours and at B is 30 hours. Calculate the total manufacturing lead time for the order. 6.5. In problem 6.4, what percentage of time is the order actually running

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!