Question: please answer A&B The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item LT (week) Amount
please answer A&B
The following table lists the components needed to assemble an end item, lead times, and quantities on hand. Item LT (week) Amount on hand End 3 0 B 1 12 UNN D 2 27 E 2 13 F 3 31 ONN H 3 Click here for the Excel Data File Endom B Da E2 H14 E 23 E Fas a. If 22 units of the end item are to be assembled, how many additional units of E ore needed? (Hint You don't need to develop an MRP plan to determine this.) b. An order for the end item is scheduled to be shipped at the start of week 17. What is the latest week that the order can be started and still be ready to ship on time? (Hint: You don't need to develop an MRP plan for this part either.)