Question: please answer all thank you! You are choosing between two projects. The cash flows for the projects are given in the following table ($ million):
please answer all thank you! You are choosing between two projects. The cash flows for the projects are given in the following table ($ million): LOADING... . a. What are the IRRs of the two projects? b. If your discount rate is 5.4%, what are the NPVs of the two projects? c. Why do IRR and NPV rank the two projects differently? Question content area bottom Part 1 a. What are the IRRs of the two projects? The IRR for project A is enter your response here%. (Round to one decimal place.) Project Year 0 Year 1 Year 2 Year 3 Year 4 A -48. 23 20 19 16 B -100. 22 42 50 62