Question: please answer all the boxes and solve it from S - Z . I dont need a full explanation just the answers please The demand

please answer all the boxes and solve it from S-Z. I dont need a full explanation just the answers please
The demand for subassembly S is 130 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 2 units of V,2 units of W, and 2 units of x. Finally, each unit of U requires 1 unit of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S,1 week to make T,2 weeks to make U,2 weeks to make V,3 weeks to make W,1 week to make x,2 weeks to make Y , and 1 week to make Z.
Click the icon to view the product structure and the time-phased product structure.
Click the icon to view the on-hand inventory.
Construct a net material requirements plan using on-hand inventory (enter your responses as whole numbers).
\table[[Item,Week,Lead Time (weeks)],[1,2,3,4,5,6,7],[S,Gross req,,,,,,,,2],[,On hand,,,,,,,],[,Net req,,,,,,,],[,Order receipt,,,,,,,
 please answer all the boxes and solve it from S-Z. I

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!