Question: please answer ASAP, I only have 15 mins. Question 5 (1 point) A work cell in a local manufacturer has a workstation with 4 machines



please answer ASAP, I only have 15 mins.
Question 5 (1 point) A work cell in a local manufacturer has a workstation with 4 machines and each unit needs to pass through each machine to be completed (in the order of machine 1--machine 2--machine 3--machine 4). The capacity of the machines are as follows, 15, 60, 40, and 20 units per hour. What is the process cycle time of the system in minutes? Note: Round your final answer to two decimal places. Question 9 (1 point) Calculate the LS of the following activity: Activity ES EF LS A 11 20 ? LF Duration ? 63 Question 10 (1 point) Calculate the slack of the following activity: Activity ES EF LS LF Slack A 12 25 32 45Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock