Question: Please answer ASAP Using the activitv list provided. draw the network diagram associated If the Design of the Website takes 22 days instead of what


Please answer ASAP
Using the activitv list provided. draw the network diagram associated If the Design of the Website takes 22 days instead of what was originally planned, the project will end un taking 45 days If the activity of Developing the New Slogan starts 3 days later than planned, the start of activity G will be delayed by 1 day If the Research for the Venue for the Launch Event doesn't start until Day 18, there will be no impact to the total project duration The New Logo Development, Development of the New Slogan and the Internal Meeting to Discuss the Launch Event must all be completed before The New Logo and Slogan can be approved