Question: PLEASE ANSWER BOTH A. & B. a. What would be your target completion week? The target completion week is week (Enter youi: response as an
PLEASE ANSWER BOTH A. & B.

a. What would be your target completion week? The target completion week is week (Enter youi: response as an integer.) b. How much would you save in total project costs with your schedule? Total Savings =$ (Enter your response as an integer.) You are the project manager of the software installation project in the table below. You would like to find the minimum-cost schedule for your project. There is a $1,000-per-week penalty for each week the project is delayed beyond week 25 . In addition, your project team determined that indirect project costs are $1,500 per week