Question: Please answer both questions. Question 7 6 . 5 pts Use this information for the next THREE questions. Activity times are in weeks. The 2

Please answer both questions. Question 7
6.5 pts
Use this information for the next THREE questions. Activity times are in weeks. The 2 missing activity times in the following network are:
A=3
R=8
What is the Latest Start Time for Activity 3?
Question 8
6.5 pts
What is the Early Finish time for Activity A?