Question: please answer c & d following the given layout on excel 1) The demand for subassembly S is 95 units in week 7. Each unit

please answer c & d following the given layout
on excel
please answer c & d following the given layout on
please answer c & d following the given layout on
1) The demand for subassembly S is 95 units in week 7. Each unit of S requires 1 unit of T and 2 units of U. Each unit of T requires 1 unit of V,2 units of W, and 1 unit of X. Finally, each unit of U requires 2 units of Y and 3 units of Z. One firm manufactures all items. It takes 2 weeks to make S, 1 week to make T, 2 weeks to make U,2 weeks to make V,3 week to make W, 1 week to make X, 2 week to make Y, and 1 week to make Z. Using the information above, a) Determine the quantity for all items required to produce 95 units b) Create a time-phase product structure c) Construct a gross material requirements plan. d) Construct a net material requirements plan using the on-hand inventory. Note: All the plans must be constructed using Microsoft Excel program. Gross Material Requirements Plan for Subassembly S Net Materials Pequirement Plan for Subassembly 5

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!