Question: PLEASE ANSWER D-F. I WILL GIVE THUMBS UP IF CORRECT Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in
PLEASE ANSWER D-F. I WILL GIVE THUMBS UP IF CORRECT
Ross Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels.
| Time (weeks) | Immediate | Time (weeks) | Immediate | ||||||||||||
| Activity | a | m | b | Predecessor(s) | Activity | a | m | b | Predecessor(s) | ||||||
| A | 4 | 9 | 12 | G | 2 | 3 | 4 | C, E | |||||||
| B | 1 | 9 | 24 | A | H | 1 | 1 | 1 | F | ||||||
| C | 8 | 12 | 16 | A | I | 5 | 5 | 5 | F | ||||||
| D | 5 | 6 | 10 | A | J | 6 | 8 | 12 | D, G, H | ||||||
| E | 1 | 2 | 4 | B | K | 1 | 1 | 4 | I, J | ||||||
| F | 6 | 9 | 20 | C, E | |||||||||||
a) The expected (estimated) time for activity C is 12 weeks. (Round your response to two decimal places.)
b) The variance for activity C is 1.781.78 weeks. (Round your response to two decimal places.)
c) Based on the calculation of the estimated times, the critical path is A - B - E - F - H - J - K
d) The estimated time for the critical path is nothing weeks. (Round your response to two decimal places.)
e) The activity variance along the critical path is ________ weeks. (Round your response to two decimal places).
f) The probability that Hopkins Hospitality will finish the project in 36 weeks or less is ________. (Enter as a probability and round your response to three decimal places).