Question: Please answer for all 9 parts for my second try, There is 2 pictures first picture shows the first try and all the questions going

Please answer for all 9 parts for my second try, There is 2 pictures first picture shows the first try and all the questions going to be asked (I got most of them wrong) . I want you to try solving all parts for the second try that has not wrong answers, it only shows part A. At the very least please do part A second try it will be the second picture.

Please answer for all 9 parts for my second try, There is2 pictures first picture shows the first try and all the questions

a) The theoretical minimum number of workstations =5 (round your response up to the next whole number). b) The assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.) Were you able to assign all the activities to workstations equivalent to the theoretical minimum workstation? c) The efficiency of the assembly line =83.3% (enter your response as a percentage rounded to one decimal place). a) The theoretical minimum number of workstations = (round your response up to the next whole number)

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!