Question: please answer in detail, and please write today's date at the end of you handwritten solution!! Suppose that a single - sampling plan with n=100
please answer in detail, and please write today's date at the end of you handwritten solution!!

Suppose that a single - sampling plan with n=100 and c=2 is being used for receiving inspection where the supplier ships the product in lots of size N=3000. Draw the OC curve for this plan. (5 Points)
Step by Step Solution
There are 3 Steps involved in it