Question: Please answer it ASAP, u do not need to step by step The cost of preparing a tender for a project is considered to be:
Please answer it ASAP, u do not need to step by step
The cost of preparing a tender for a project is considered to be: it of Select one: O a. Overhead O b. Profit O c. An indirect cost O d. Contingency O e. A direct cost s page Next page