Question: please answer it fast 6 pts Question 1 Assume that a project has the following activities and activity times (in months). The project is completed
please answer it fast
6 pts Question 1 Assume that a project has the following activities and activity times (in months). The project is completed when activities F and G are both complete. Activity BCDE F G Immediate Predecessor A C, B C, B DE Time 462 6 3 3 5 (a) Find the critical path. (Enter your answers as a comma-separated list with one space between comma and the next letter, e.g., B, E, G) A.C.E.G (b) The project completion time is 14 months. (c) The project must be completed in 1.5 years. Do you anticipate dithculty in meeting the deadline? YES or NO? YES
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock