Question: Please Answer Item D and Show Work You need to schedule 10 units of product Apha for delivery in 6 weeks. Three units of D

Please Answer Item D and Show Work
 Please Answer Item D and Show Work You need to schedule

You need to schedule 10 units of product Apha for delivery in 6 weeks. Three units of D and 2 units of F are required for each Alpha. The lead time for Alpha is 1 week Lead time for D is 1 week and lead time for F is 2 weeks Click the icon to view the product structure Cick the icon to view the time-phused product structure Construct a net msterial requirements plag i there are 2As on hand and 4D s (enter your responses as whole numbers)