Question: Please answer jestion 14+ 0 pollits) At some point in the life of a project, the project manager determined the follow data on a $1.250,000

Please answer

Please answer jestion 14+ 0 pollits) At some point in the life

jestion 14+ 0 pollits) At some point in the life of a project, the project manager determined the follow data on a $1.250,000 authorized budget project: amount of earned value $350,0 At that point, the value of the planned work was $750,000, and actual cost was $750,000. Based on this information, the Schedule Performance Index for this project was: 0.28 0.47 0.53 0.60