Question: PLEASE ANSWER PART A AND B Question Completion Status: Use the activity on-arrow diagram below to answer the following two questions, E (4) A (4)
PLEASE ANSWER PART A AND B
Question Completion Status: Use the activity on-arrow diagram below to answer the following two questions, E (4) A (4) G (4) C (3) 1(3) O B (3) F (4) H (2) D (3) What is the length of the critical path? A 15 days B. 16 days C. 17 days What is the slack for task E! Question Completion Status: A. 15 days What is the length of the critical path? What is the slack for task E? B. 16 days C. 17 days D. 18 days E. 19 days zero days Gone day H two days 1. three days 1. four days