Question: Please answer part a and part b We are evaluating a project that costs $717,000, has a life of fourteen years, and has no salvage

Please answer part a and part b
We are evaluating a project that costs $717,000, has a life of fourteen years, and has no salvage value. Assume that depreciation is straight-line to zero over the life of the project. Sales are projected at 135,000 units per year. Price per unit is $39, variable cost per unit is $26, and fixed costs are $724,887 per year. The tax rate is 23 percent, and we require a return of 21 percent on this project. The projections given for price, quantity, variable costs, and fixed costs are all accurate to within +/16 percent. a. Calculate the best-case NPV. Best case b. Calculate the worst-case NPV
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
