Question: please answer part b. with Excel, thanks! End item P is composed of three subassemblies: K, L and W. K is assembled using 3 Gs

please answer part b. with Excel, thanks!

End item P is composed of three subassemblies: K, L and W. K is assembled using 3 Gs and 4 Hs; L is made of 2 Ms and 2 Ns; and W is made of 3 Zs. On-hand inventories are 20Ls, 40Gs, and 200 Hs. Scheduled receipts are 10Ks at the start of week 3, 30 Ks at the start of week 6, and 200 Ws at the start of week 3. One hundred Ps will be shipped at the start of week 6, and another 100 at the start of week 7. Lead times are two weeks for subassemblies and one week for components G, H and M. Final assembly of P requires one week. The minimum order size for H is 200 units. For rest of the items, assume lot for lot ordering.

a. Develop a product structure tree

b. Develop MRP tables for K, G and H

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!