Question: please answer parts A, B and C please!!! 1. (3 points total, 70% content, 30% communication quality). The data in the table below are for

please answer parts A, B and C please!!!
please answer parts A, B and C please!!! 1. (3 points total,

1. (3 points total, 70% content, 30% communication quality). The data in the table below are for a 52-week project with a budget of $2 million. (Note: All values are cumulative, in thousands of dollars.) a. Cost variances and schedule variances for each week b. Summary (project-level) earned value measures for week 15, including: cost and schedule variance, cost and schedule variance %, CPI and SPI, EAC, ETC, VAC, TEAC, Percent complete, Percent money spent C. An overall assessment of project performance based on parts a & b: i. How well for how poorly) is the project performing? ii. What corrective actions, if any, would you suggest and why? If no corrective actions are currently needed, suggest a monitoring strategy you should use to determine when to act (e.g., at what point should corrective action be taken and how would you know?). se %, CPI and SPI, EA Week BCWS BCWP ACWP CV SV 55 50 27 2 72 60 39 3 88 80 68 4 119 105 89 5 131 120 112 6 141 135 131 7 150 151 8 201 175 189 9 252 220 229 10 275 260 271 302 295 301 12 349 340 343 13 384 360 362 14 423 395 395 15 490 460 457 163 11 UNWN

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Finance Questions!