Question: Please answer question #2, SHOWING ALL WORK ACCORDINGLY ON ALL PARTS. Thank you! The following activities are part of a project to be scheduled using

Please answer question #2, SHOWING ALL WORK ACCORDINGLY ON ALL PARTS. Thank you!

Please answer question #2, SHOWING ALL WORK

The following activities are part of a project to be scheduled using CPM: ACTIVITY IMMEDIATE PREDECESSOR TIME (WEEKS) B UOWU ONDI B, D MNNM 6 3 7 2 4 3 7 E G E, F b. What is the critical path? A-C-D-E-G O A-B-E-G O A-C-D-F-G c. How many weeks will it take to complete the project? Number of weeks d. How much slack does activity B have? Slack of activity B weeks