Question: please answer question 5 and 6 Please solve the following question for Project Management course. Ine ronowing table presents the activities for a small construction
please answer question 5 and 6
Please solve the following question for Project Management course. Ine ronowing table presents the activities for a small construction project: Duration 30 12 8 4 Activity Predecessor A B D A E A F 80 G F. H 1 EG 3 EG LH L K 6 4 3 6 12 8 10 You need to 1. Comprende agram 2. On the dagar.com the four schedule times, US, U) 1. Calcule TV and for it (Tabulate your tower.ee the critical path 3. What the number of day that. Cand Han bertand without fecting the date Task No The maximum number of days that can be delayed H Task No. F The maximum number of days that can be delayed 1 D
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
