Question: Please answer question3. There is an error in question 3. The revised question 3: If it is necessary to crash the project by 40 days,

Please answer question3. There is an error in

Please answer question3. There is an error in

Please answer question3.

There is an error in question 3.

The revised question 3:

If it is necessary to crash the project by 40 days, how would Hill do so, and at what costs? The difference between OPTIMISTIC time estimates and MOST LIKELY time estimates can be used as crash times.

Southwestern University: (A)* Southwestern University (SWU), a large state college in Stephenville, Texas, 30 miles southwest of the Dallas/Fort Worth metroplex, enrolls close to 20,000 students. In a typical town-gown relationship, the school is a dominant force in the small city, with more students during fall and spring than permanent residents. A longtime football powerhouse, SWU is a member of the Big Eleven conference and is usually in the top 20 in college foot- ball rankings. To bolster its chances of reaching the elusive and long-desired number-one ranking, in 2009, SWU hired the leg- endary Phil Flamm as its head coach. ACTIVITY DESCRIPTION PREDECESSOR(S) OPTIMISTIC 20 B A 20 TIME ESTIMATES (DAYS) MOST LIKELY PESSIMISTIC CRASH COST/DAY 30. 40 $1,500 65 80 3,500 60 100 4,000 50 100 1,900 30 35 9,500 0.1 0.1 0 A 50 D 30 E B 25 F E Bonding, insurance, tax structuring Foundation, concrete footings for boxes Upgrading skybox stadium seating Upgrading walkways, stairwells, elevators Interior wiring, lathes Inspection approvals Plumbing Painting Hardware/AC/metal workings Tile/carpet/windows Inspection Final detail work/cleanup 0.1 25 G DF 30 35 H 10 20 30 1 2,500 2,000 2,000 6,000 H 20 25 60 J H 8 10 12 K J 0.1 0.1 0.1 0 L I, K 20 25 60 4,500 One of Flamm's demands on joining SWU had been a new of $10,000 per day for running late is nothing compared to what stadium. With attendance increasing, SWU administrators began Coach Flamm will do to you if our opening game with Penn State to face the issue head-on. After 6 months of study, much politi is delayed or canceled. cal arm wrestling, and some serious financial analysis, Dr. Joel Wisner, president of Southwestern University, had reached a decision to expand the capacity at its on-campus stadium. Adding thousands of seats, including dozens of luxury sky- boxes, would not please everyone. The influential Flamm had argued the need for a first-class stadium, one with built-in dormi- Discussion Questions tory rooms for his players and a palatial office appropriate for the coach of a future NCAA champion team. But the decision 1. Develop a network drawing for Hill Construction and was made, and everyone, including the coach, would learn to live determine the critical path. How long is the project with it. expected to take? The job now was to get construction going immediately after the 2015 season ended. This would allow exactly 270 days until 2. What is the probability of finishing this project in less the 2016 season opening game. The contractor, Hill Construction than 265 days? (Bob Hill being an alumnus, of course), signed his contract. Bob 3. If it is necessary to crash the project by 40 days, how Hill looked at the tasks his engineers had outlined and looked would Hill do so, and at what costs? The difference President Wisner in the eye. "I guarantee the team will be able to between optimistic time estimates and pessimistic take the field on schedule next year," he said with a sense of con time estimates can be used as crash times. fidence. I sure hope so," replied Wisner. "The contract penalty

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!