Question: please answer questions 1-6. question are located at the bottom Case Study 2: Elongated Works: Elvis Elangoe, the project manager, measured the following eight weeks

please answer questions 1-6.
please answer questions 1-6. question are located at the bottom Case Study
question are located at the bottom
2: Elongated Works: Elvis Elangoe, the project manager, measured the following eight

Case Study 2: Elongated Works: Elvis Elangoe, the project manager, measured the following eight weeks after the start of the project at Elongated Works Inc. Questions to Answer: 1. How does the project progress compare to the project plan? Choose one metric used in Earned Value Analysis and explain. 2. What do we expect project cost to be now? 3. What are the cost and schedule performance indices? What can you infer from these indices? 4. What is the estimate to complete the project? 5. What is the future of this project? Compute TCPI. 6. Show a graph of planned value ("PV"), earned value ("EV"), and actual cost ("AC"). Questions to Answer: 1. How does the project progress compare to the project plan? Choose one metric used in Earned Value Analysis and explain. 2. What do we expect project cost to be now? 3. What are the cost and schedule performance indices? What can you infer from these indices? 4. What is the estimate to complete the project? 5. What is the future of this project? Compute TCPI. 6. Show a graph of planned value ("PV") earned value

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!