Question: Please answer questions 2 and 3. 1. A certain project has three activities on its critical path. Activity A's normal completion time is five days.

Please answer questions 2 and 3.

Please answer questions 2 and 3. 1. A certain project has three

1. A certain project has three activities on its critical path. Activity A's normal completion time is five days. It can be crashed to three days at a cost of $500. Activity B's normal completion time is six days, and it can be crashed to four days at a cost of $50. Activity C's normal completion time is eight days. It can be crashed to three days at a cost of $1,000. Which activity should the project manager crash and by how many days? How much will it cost? 2. Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days, and so on until it is in an all-crash mode. Identify how much it would cost for each day you crash the schedule. 3. Using the data below, create the project schedule using normal times. Determine the order in which you would crash the project one day, two days, and so on until it is in an all-crash mode. Identify how much it would cost for each day you crash the schedule

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!