Question: Please Answer! Thanks!! (3 points) Problem 5: A consulting project has an actual cost in month 10 of $23,000, a scheduled cost of $17,000, and

Please Answer! Thanks!!

Please Answer! Thanks!! (3 points) Problem 5: A

(3 points) Problem 5: A consulting project has an actual cost in month 10 of $23,000, a scheduled cost of $17,000, and a value completed of $20,000. Find the schedule and cost variances and the three indexes (CPI, SPI, CSI)