Question: Please answer the attached question GTech Eng. Ltd . is planning to modernise and expand its current main office branch in London. Details of the
Please answer the attached question GTech Eng. Ltd is planning to modernise and expand its current main office branch in London.
Details of the activities and required time for the modernisation and expansion of the project are
shown below:
GTech Eng. Ltd wishes to know whether the project can be completed over a week period with
an additional cost. The following information has been obtained for normal and crash duration of
the project.
Manaqerial report:
Develop a report that presents the activity schedule and expected project completion time to
modernise and expand its current office, more specifically:
Performance of an eventbased analysis, ie obtaining earliest event times and latest
event times inserting them appropriately into the diagram and, hence, obtaining the
critical path and project duration.
Performance of an activitybased analysis, ie obtaining EST, LST EFT, LFT total float
TF and free float FF showing all these values in a table and obtaining the critical path
and project duration.
Crashing decisions to meet the desired week completion time at the least possible cost
making the crashing decisions and developing an activity schedule onebyone and taking
least cost slope first. Show the extra project cost required to meet the week completion
time including all critical paths.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock