Please answer the attached question GTech Eng. Ltd. is planning to modernise and expand its current main office branch in London.
Details of the activities and required time for the modernisation and expansion of the project are
shown below:
GTech Eng. Ltd. wishes to know whether the project can be completed over a 30-week period with
an additional cost. The following information has been obtained for normal and crash duration of
the project.
Manaqerial report:
Develop a report that presents the activity schedule and expected project completion time to
modernise and expand its current office, more specifically:
Performance of an event-based analysis, i.e., obtaining earliest event times (TE) and latest
event times (TL), inserting them appropriately into the diagram and, hence, obtaining the
critical path and project duration.
Performance of an activity-based analysis, i.e., obtaining EST, LST, EFT, LFT, total float
(TF) and free float (FF), showing all these values in a table and obtaining the critical path
and project duration.
Crashing decisions to meet the desired 30-week completion time at the least possible cost
making the crashing decisions and developing an activity schedule one-by-one and taking
least cost slope first. Show the extra project cost required to meet the 30-week completion
time including all critical paths.
 Please answer the attached question GTech Eng. Ltd. is planning to

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!