Question: please answer The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Foliowing are five projects under considerotion. Using
please answer


The Custom Bike Company has set up a weighted scoring matrix for evaluation of potential projects. Foliowing are five projects under considerotion. Using the scoring matrix above, what score would you give to each project? Which project would you choose first? If the weight for "Strong Sponsor" is changed from 2 to 5 , what score would you give to each project? Now, which project would you choose first? Why is it important that the weights mirror critical strategic factors