Question: Please answer the following question, based on this information. If he uses the earliest due date first ( EDD ) priority rule to schedule these
Please answer the following question, based on this information.
If he uses the earliest due date first EDD priority rule to schedule these jobs, what is the makespan of this schedule?
A hours
B hours
C hours
D hours
E hours