Question: Please Answer the Question in the picture. Do not just copy answer from another question and paste it into this. I am uploading this question

Please Answer the Question in the picture. Do notPlease Answer the Question in the picture. Do notPlease Answer the Question in the picture. Do notPlease Answer the Question in the picture. Do notPlease Answer the Question in the picture. Do not

Please Answer the Question in the picture. Do not just copy answer from another question and paste it into this. I am uploading this question for the Third Time. Previously they just copied answer from another question and pasted them in this. I do not want that.

An MRP Explosion - Brunswick Motors scheduling Brunswick's engine assembly operations, and decided to prepare an example to illustrate the use to Time-Phased Requirements Model 1000 engine to be assembled each week during the past twelve weeks, and is shown below. Engine Assembly Master Schedule engine. These two components, the Gear Box and the Input Shaft, are shown in the Product Structure Diagram shown here. Phil noted that the Gear Box is assembled by the Subthe Gear Box. and the Machine Shop. and the Machine Shop. The manufacturing lead times required to produce the Gear Box and Input Shaft components are also indicated in the Product Structure Diagram. Note that two weeks are required to produce a batch of Gear Boxes, and that all of the Gear Boxes must be delivered to the assembly line parts stockroom before Monday morning of the week in which they are to be used. Likewise, it takes three weeks to produce a lot of Input Shafts, and all of the shafts that are needed for the production of Gear Boxes in a given week must be delivered to the Sub-Assembly Department stockroom before Monday morning of the week. In preparing the MRP example Phil made the following assumptions: - Twenty-two gear boxes are on hand at the beginning of Week 1 , and eight gear boxes are currently on order to be delivered at the start of Week 2. - Forty-five input shafts are on hand at the start of Week 1, and 25 are scheduled for delivery at the beginning of Week 2. Initially, assume that Phil wants to minimize his inventory requirements. Assume that each order will be only for what is required for a single period Gear Box Requirements \begin{tabular}{|l|l|l|l|l|l|l|l|l|l|l|l|l|} \hline \multicolumn{1}{|c|}{ Week: } & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 & 9 & 10 & 11 & 12 \\ \hline Gross Requirements & & & & & & & & & & & & \\ \hline Scheduled Receipts & & & & & & & & & & & & \\ \hline Projected Available Balance & & & & & & & & & & & & \\ \hline Net Requirements & & & & & & & & & & & & \\ \hline Planned Order Receipt & & & & & & & & & & & & \\ \hline Planned Order Release & & & & & & & & & & & & \\ \hline \end{tabular} Input Shaft Requirements \begin{tabular}{|l|l|l|l|l|l|l|l|l|l|l|l|l|} \hline \multicolumn{1}{|c|}{ Week: } & 1 & 2 & 3 & 4 & 5 & 6 & 7 & 8 & 9 & 10 & 11 & 12 \\ \hline Gross Requirements & & & & & & & & & & & & \\ \hline Scheduled Receipts & & & & & & & & & & & & \\ \hline Projected Available Balance & & & & & & & & & & & & \\ \hline Net Requirements & & & & & & & & & & & & \\ \hline Planned Order Receipt & & & & & & & & & & & & \\ \hline Planned Order Release & & & & & & & & & & & & \\ \hline \end{tabular} Part Cost Gear Box Setup =$85/ order Inventory Carrying Cost =$2/ unit / week Input Shaft Setup =$40 /order Inventory Carrying cost =$2/ unit / week Gear Box gross requirements. What are the total costs of schedule for Gear Box based on the L4L technique? - Having the completed MRP table for Gear Box, based on the L4L lot sizing technique, answer the following questions: Question 2. Complete the MRP table using the lot-for-lot ( LL) lot sizing technique for Input Shaft. What are the total costs of schedule for Input Shaft based on the L technique? Question 3. Complete the MRP table using the EOQ lot sizing technique for Input Shaft . Assume the total annual demand for Input Shaft is D=2288 units. what are the total costs of schedule for Input Shaft based on the EOQ technique? Question 4.Complete the MRP table using the least total cost (LTC) lot sizing technique to determine the first planned order quantity for Input Shaft. The second order quantity must meet the requirements of Input Shaft to the end of week 12 . What are the total costs of schedule for Input Shaft? Question 5. Complete the MRP table, using the least unit cost (LUC) lot sizing technique to determine the first planned order quantity for Input Shaft. The second order quantity must meet the requirements of Input Shaft to the end of week 12. What are the total costs of schedule for Input Shaft

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!