Question: Please answer the question listed above. Thank you! Question 1 Draw a project map, given the following set of tasks and predecessors. For this question,

Please answer the question listed above. Thank you!
Question 1 Draw a project map, given the following set of tasks and predecessors. For this question, it is not necessary to include the earliest and latest start and finish times (hence why the task length information is omitted). Task Predecessors A M B A A Start Finish C D E F G B,C D,E FStep by Step Solution