Question: Please answer the questions a b c d Question 2 (35 marks) Given the following table displaying the logical connections of activities and the time

Question 2 (35 marks) Given the following table displaying the logical connections of activities and the time estimates of a project: Dependency Activity A B D E F G MOA Time (Days) a m b 1 3 4 3 5 8 6 7 9 2 3 4 2 4 6 3 8 9 3 4 6 A B B A D.E C,F Construct the network diagram for the project. Also, calculate the EST and LST of the events and mark on the diagram. (14 marks) a. b. Calculate the te,s", TF, FF, IF and state the critical path. (Show all your calculation steps). (9 marks) c. Determine the probability of the project's completion in 20 days. (6 marks) d. By what date would there be a 90% chance of completion? (6 marks) Question 2 (35 marks) Given the following table displaying the logical connections of activities and the time estimates of a project: Dependency Activity A B D E F G MOA Time (Days) a m b 1 3 4 3 5 8 6 7 9 2 3 4 2 4 6 3 8 9 3 4 6 A B B A D.E C,F Construct the network diagram for the project. Also, calculate the EST and LST of the events and mark on the diagram. (14 marks) a. b. Calculate the te,s", TF, FF, IF and state the critical path. (Show all your calculation steps). (9 marks) c. Determine the probability of the project's completion in 20 days. (6 marks) d. By what date would there be a 90% chance of completion? (6 marks)
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts