Question: Please answer the questions Objective Questions 15 on p. 165 (Chapter 5) Step 1: Construct a CPM diagram Step 3: Compute the critical path Sten

Please answer the questions
Objective Questions 15 on p. 165 (Chapter 5) Step 1: Construct a CPM diagram Step 3: Compute the critical path Sten 2: Calculate costs per dav to expedite Step 4: Calculate costs per day to expedite Step 5: Plot cost curves if any