Question: please answer the whole question without theory explanation , just answer it with numbers and calculations Q3. The University is looking to purchase a new

please answer the whole question without theory explanation , just answer it with numbers and calculations
Q3. The University is looking to purchase a new resource management system and each vendor has provided some information on implementation problems reported and the estimated time for the problem specialist to arrive and fix the problem. The data from the vendors was collected over 6 weeks. Each workweek is 35 hours, Below is the data from the vendors, which vendor offers the best system for the university with the best per hour reliability. (Use 3 decimals for Availability) Travel time for specialist 120 minutes 60 minutes VendorNumber of Problems Time to Fix Problem Vendor A 65 1.5 Hours Vendor B 105 40 minutes Vendor C 140 70 minutes 120 minutes SolutionStep by Step Solution